SIGNING OF TRANSACTION AGREEMENT WITH THE MUNICIPALITY OF AGIOS NIKOLAOS

Contract signing for the operation entitled:

«SUPPLY AND INSTALLATION OF A TELEMETRY & LEAKAGE CONTROL SYSTEM IN THE WATER SUPPLY NETWORK OF THE MUNICIPALITY OF AGIOS NIKOLAOS». 

Budget 1,700.00.00€ without VAT
Financing O.P.- Transport Infrastructure, Environment and Sustainable Development

SYSTEM OBJECTIVE IS:

The objective of the act is the rational use, energy saving, as well as the qualitative management and control of water resources in all areas of the Municipality of Agios Nikolaos where water supply is the responsibility of DEYAN.

THE OBJECT OF THE CONTRACT INCLUDES THE FOLLOWING WORKS:

  •  The installation of flow, pressure and energy measuring instruments in seventeen (17) existing local controlstations and their integration into the new SCADA for the needs of the Leak Control
  •  The installation of eighty-five (85) new control stations in boreholes, pumping stations and tanks with local automation panel, flow meters, tank level and borehole level in main underground aquifers, where all the water produced and supplied to the consumption will be recorded.
  •  The installation of chlorination and residual chlorine systems in tanks to check and record their proper functioning.
  •   The installation of fully equipped smart wells with flow, pressure and pressure measuring instruments and pressure regulation with electronic pressure reducing valve, which will be installed at points of the internal network for the regulation of water supply zones after the calculation of the model to be carried out by the contractor.
  • The design and implementation of the implementation of a suitable hydraulic strategic and detailed simulation model for the redesign of new supply zones and leakage control in order to improve the supply of the Municipality of Agios Nikolaos with a more rational water supply system taking into account the studies of the Service. The contractor, after the completion of the field work with its own systems, will have to install pressure, measurement and flow regulation systems in selected points of the internal networks of the Municipality of Agios Nikolaos where they will inform in case of leakage.
  • The installation of a Central Control Station (CCS) of two servers, for the development of the remote control and leakage software. The objective is to collect all the data from the local facilities and to process them in a comprehensive way in order to provide a direct and global presentation of water balances, system management under water scarcity, data analysis for stock management, strategy formulation, demand forecasting, decision support and water resources operation rules. It also includes a computer module for the implementation of the Leakage System.
  • The design, supply, delivery, on site, unloading and storage on site, moving and lifting, construction, testing and commissioning of all the equipment described in the text and drawings as well as the required interconnection works with the existing installation, as specified in the Technical Specifications.
  • The full operation and maintena nce of all systems to be installed for 10 years according to the NIS, which is not an eligible expenditure and the payment will be made per year from D.E.Y.A.A.N.'s own resources.